
Mikvah Building Checklist
It's important to note that each Mikvah expert and contractor may have their unique approach and specific steps in the construction process.
Therefore, this checklist represents a general construction guideline encompassing various essential steps, some of which might not be applicable to every Mikvah.
Updates and revisions to this guide will be made as more information is gathered and confirmed.
Research and building team
Rov
Mikvah Expert
Contractor
Designer
Building the bor
Cradle
Built the frames
Put in rebar in everything before the poor
The wire (grounding) is attached to the rebar
Put in the Pipe Wall Sleeves (wires for heating, filter and LED lights etc)
Poured the mikvah
Waterproof test
Added the floor for the top bor
Poured the steps
Attached the railing
Attached the wires to all the places ( Railing, Heating, )
Tiled the bor
Added the heating element
Thermostat sensor (aquastat)
Filter
The Rov Checked it over
Getting the Rainwater
The Rov approved the roof design and material
Attached the gutter
Pipes from the roof
Otzar
(Catch Box to direct the water)
Hamshachas
Cover for the Hashachas
Mikvah Room
Lighting
Exhaust fan
Faucet to add water to the mikvah
Drain
Tiled
Hooks ( to place robe & towel)
Maintenance room
Boiler
Water Heater
HVAC
Filter control box
Washer Dryer
Prep Room
Lighting
Exhaust fan
Tub
Shower
Sink
Vanity
Toilet
Towel Warmers
Hooks
Entrance/ Lobby
Sink
Intercom/ speaker
General Building Guide
1. Prepare Construction Site and Pour Foundation
Builder applies for and acquires permits.
Construction crew levels site.
Builder puts up wooden forms for the temporary foundation.
Footings are installed.
Waterproofing and plumbing are installed.
Inspection #1
2. Complete Rough Framing
Floor system, walls and roof system are completed.
Sheathing is applied to exterior walls and covered with protective wrap.
3. Complete Rough Plumbing, Electrical and HVAC
Pipes and wires
Sewer lines and vents
Water supply lines
Bathtubs and shower units
Ductwork for HVAC system
HVAC vent pipes
Electrical wiring and receptacles
Inspections #2, #3, and #4
4. Install Insulation
5. Complete Drywall and Interior Fixtures; Start Exterior Finishes
Drywall is hung and taped.
The primer coat of paint is applied.
Exterior finishes are installed.
6. Finish Interior Trim; Install Exterior Walkways and Driveway
Doors, windowsills and decorative trim are installed.
Cabinets, and vanities are installed.
The final coat of paint is applied.
7. Install Hard Surface Flooring and Countertops; Complete Exterior Grading
Ceramic tile, vinyl and wood flooring are installed.
The exterior finish grading is completed to ensure proper drainage away from the home and to prepare the yard for landscaping.
8. Finish Mechanical Trims; Install Bathroom Fixtures
Light fixtures, outlets and switches are installed, and the electrical panel is completed.
HVAC equipment is installed and registers completed.
Sinks, toilets and faucets are put in place.
9. Install Mirrors and Shower Doors; Finish Flooring and Exterior Landscaping
Mirrors, shower doors and carpeting are installed and final cleanup takes place.